With
half of the electricity supply still imported and demand rising, it
is vital to boost output for industrial development
rivatisation
and foreign investment are seen as the key solutions to energy shortages
in Bosnia and Herzegovina, although industry officials recognise that
this is likely to be a lengthy process.
First, the industry must be restructured to make it more attractive
to potential bidders, an issue that is currently being addressed by
a feasibility study due for completion in February.
The question is whether a majority interest in the electricity industry
could be sold off as one business, or whether it should be split up
prior to any sale into three businesses covering power generation, transmission
and local distribution.
Under
the first option, a 67 per cent interest in the industry would go up
for international tender, with a further 15 per cent offered as shares
to the public. The remainder, consisting of the transmission network,
would be retained by the state, giving it strategic control over the
sector.
Increasing the supply of energy and, above all, electricity is considered
vital for the reconstruction of the economy in the wake of the civil
war. Much of the electricity generation and distribution capacity was
damaged or destroyed, and it has taken years to rebuild the industry.
Reconstruction
was carried out under a $234 million project called Power III, which
was led and partly financed by
the World Bank with support from the European Bank for Reconstruction
and Development (EBRD), the EU and other donors. The plan was also partly
intended to integrate the power grid of Bosnia and Herzegovina with
the EU.
At present, installed power-generation capacity is 3,867MW, more than
half of which is produced by hydroelectricity plants. Bosnia and Herzegovina
lacks reserves of oil and natural gas, and its only fossil-fuel resources
are coal and lignite or brown coal.
However,
the coal-mining industry was also severely damaged during the conflict,
and output has not fully recovered to its pre-war level. Production
is running at an estimated four million tonnes a year, compared with
12 million tonnes in 1990 and a peak of 18 million tonnes following
modernisation in the 1970s.
Efforts to restore output have also been hampered by workers unrest
and strikes in response to proposals that the industry be restructured
and privatised.
Although the process of repairing the sector is almost complete, Bosnia
and Herzegovina is unable to meet its needs. The balance of payments
is burdened with the cost of importing oil for refining and natural
gas from Russia, and the electricity industry is not self-sufficient.
Elektroprivreda,
one of the three state-owned power-supply companies, is based in Mostar
and has five hydropower plants with combined capacity of 762MW, but
it is unable to produce enough electricity to cater for all its customers.
|

Zaric
‘They
need to undo the monopolies so that it is a product like
any other’
|
|
 |
We
have to import 50 per cent of our electricity, says general manager
Matan Zaric. What we
produce is sufficient for general consumption, but not for industrial
consumption as well.
He draws a direct connection between the need for reform and the industrys
inability to keep up with demand. At the moment we are importing
because the liberalisation of the market hasnt been implemented
in Bosnia and Herzegovina as yet, he says.
While waiting for the reforms to be introduced, power companies like
Elektroprivreda are operating as though the market has already been
liberalised. The company has issued international bid tenders for power
supplies and new plants in an attempt to anticipate sharply rising demand
in the residential sector.
Our
estimate is that during the next three or four years we will have to
build an additional three or four hydropower plants so that we can keep
up with rising household consumption, so we have directed all our strengths
towards meeting this goal, says Mr Zaric.
A new 30MW plant is being built at Pec-Mlini and there are plans for
another 30MW facility at Mostarsko Blato, which is awaiting planning
permission.
Electricity prices remain high in Bosnia and Herzegovina, but Mr Zaric
expects these to fall as the market opens up and small electricity-producing
firms are set up.
He
forecasts that electricity distribution companies will be established
at the level of local government. These companies will maintain
the infrastructure and sell electricity to the customers, he says.
I hope that our customers will soon be able to make their own
decisions concerning which electricity distributor they want to have.
As for the utilities the big companies dominating the market
Mr Zaric says they are also facing a period of change. They
need to undo the monopolies, so that electricity becomes a product like
any other, he explains.
Like others in the industry, he has some misgivings about how far the
sector should be reformed, even as the industry prepares for privatisation
in February.
There
has been strong resistance to this because of some of the experiences
seen in neighbouring countries like Poland and Slovakia, where the privatisation
process was carried out badly, he says.
Whereas the government appears to be heading in the direction of a wholesale
transfer of the sector into private hands, Mr Zaric believes the state
should retain control over production facilities such as power plants.
After all, he adds, these are strategic facilities.